The MRC du Haut-Saint-Laurent has awarded more than $3.5 million in contracts to carry out waterway maintenance projects in seven municipalities this fall.
A total of 14 contracts covering nearly 76 kilometers of waterways has been signed, addressing 22 requests submitted by the municipalities of Dundee, Sainte-Barbe, Saint-Anicet, Godmanchester, Très-Saint-Sacrement, Hinchinbrooke, and Ormstown. The work will help to protect farmland by managing and maintaining the free flow of surface water while ensuring the proper functioning of the region’s land drainage systems.“Maintaining waterways is a major responsibility of the MRC,” said MRC du Haut-Saint-Laurent prefect and Franklin mayor Yves Métras. “The work being carried out this fall helps maintain essential infrastructure, while addressing the needs expressed by the municipalities concerned,” he explained.
The work now requires the simultaneous coordination of the 14 contracts, which were approved in a flurry of resolutions passed during the regional council’s regular meetings on June 17 and Aug. 19, as well as at an extraordinary meeting on July 22. It involves working with five specialized contractors, as well as an engineering consultant who is responsible for technical support and supervision of the work.
Lengthy delays
Now that the work is underway, the MRC has acknowledged that the processing time for some of the 22 applications extended over several years. David Rousseau, who is responsible for waterway management with the MRC, explained that the delays were caused by a combination of factors including changes in legislative frameworks and the various steps to prepare and validate the applications. “The goal was to ensure that the applications could move forward on a complete and compliant basis,” he explained.
The timeline for the projects has long been a point of contention between the MRC and the Haut-Saint-Laurent syndicate of the Union des Producteurs Agricoles (UPA). Rousseau acknowledged this, while noting that the “MRC and the UPA share a common concern regarding the maintenance of waterways and the search for solutions that address the realities of the agricultural sector.” He confirmed that discussions with the UPA are ongoing, and “in a spirit of collaboration.”
Local UPA president Éric Leboeuf agreed, saying the union is pleased to see several projects moving forward at the same time. “There is still a lot left to do,” he cautioned, “but we have had good discussions with the new director general and the team on the ground.”
He suggested the issue gained traction following recent pressure tactics applied by the local union, which included an access to information request, complaints, and an appeal to the municipalities for support.
“We are very happy with the current council of mayors,” Leboeuf added. “The mayors are very aware of agricultural issues – not just regarding the cleanup of waterways, but regarding many other projects and challenges.”
“There is still an issue with communication, but I am confident it will be addressed,” he said, referring specifically to a public list of waterway projects on the MRC’s website which is updated periodically to reflect the status of the files. The most recent applications on the list date back to 2023; however, the MRC has confirmed that new applications have been submitted and are being assessed.
“We know the files are moving forward, and we’re happy about that, but that was the bare minimum we were asking for,” said Leboeuf, who suggests the UPA will be following up on the status of new applications.
Municipal collaboration
All the work on waterways carried out by the MRC complies with applicable environmental requirements and is done in collaboration with the municipalities involved. The MRC manages the contracts; however, it is the municipalities that cover the costs associated with the work.

Several of the projects are shared between two or more municipalities as the work is taking place on waterways that flow across municipal lines. In these cases, the percentage of the total cost has been calculated by the MRC, and each municipality will be invoiced accordingly.
A resolution passed during the Aug. 19 regional council meeting confirmed that some of the municipalities affected by the projects currently underway do not have the necessary funds to cover the associated costs. The mayors resolved unanimously to allow the MRC to draw on a $1.5 million line of credit to pay the invoices for waterway work and bill the municipalities for any amounts advanced. It is not clear whether any of the affected municipalities have requested the use of these funds.
According to the MRC, the investments made and the scale of the work now underway demonstrate the regional government’s commitment to waterway management. In a statement, the MRC confirmed that it will continue to collaborate with the municipalities to sustainably manage the waterway network, “for the benefit of the region and the activities that depend on it.”
The work on all 22 of the approved projects is expected to be completed by the end of the year.