Sainte-Barbe to invest nearly $3.8 million on road infrastructure

Construction work will soon begin in Sainte-Barbe where the municipality recently announced a $3.8 million project to improve its road network while improving access to the town hall.

The work will involve the complete repaving of a 4.5-kilometre stretch of Chemin de l’Eglise, repairs to the Montée du Lac roadway and sidewalks, the redevelopment and paving of the town hall parking area, and the installation of a green space outside the municipal building.

The municipality secured over $1.5 million in financial assistance from the provincial government to carry out the project, including $1,171,054 from the Programme d’Aide à la Voirie Locale (PAVL) and an additional $380,000 from the Programme d’Aide Financière du Fonds de la Sécurité Routière (PAFSR).

To complete the project’s financing, the municipality adopted a borrowing bylaw for $2,223,087, which was approved by the Ministère des Affaires Municipales et de l’Habitation (MAMH) on June 8.

The contract for the project has been awarded to Ali Excavation, and the work will be carried out under the supervision of the Shellex engineering firm. A kickoff meeting took place on June 22, where it was confirmed that construction will start at the end of August.

 

Three adults stand on a residential street, holding an orange road‑work sign showing a worker digging.
Saint Barbe mayor Daniel Pinsonneault was joined by MNA Carole Mallette and councillor François Gagnon to confirm the start of a $38 million project to repave the road network in the village as well as the parking area at the town hall PHOTO Municipality of Sainte Barbe

 

The paving work on the Chemin de l’Église will address the deterioration of the road surface and the numerous potholes that have developed in recent years. Culverts along this stretch will be replaced, and the sidewalks in the village centre will also be rebuilt.

The road surface on Montée du Lac will be repaved between the intersections of Rue des Moissons and Chemin de l’Eglise. All the sidewalks along this route will be rebuilt as well.

The municipal parking lot will be paved and redesigned, so the entrance and exit are more clearly defined to improve the flow of traffic.

The project also includes the creation and landscaping of a small green space in front of the town hall. The municipality is working with the Conseil regional de l’environnement de la Montérégie on this aspect of the project.

A public consultation has begun to gather residents’ input on landscaping, such as the vegetation and amenities to be included. The installation of street furniture is also being planned. (SR)

Latest stories

Police presence increased in Ormstown following fires

Fourth suspicious blaze in Ormstown consumes pizzeria

Sarah Rennie

One person arrested after 4th local pizzeria is attacked

Leave a comment

* By using this form you agree with the storage and handling of your data by this website.