Ministry approves wind energy bylaw for Beauharnois-Salaberry

The Ministry of Municipal Affairs has approved an MRC de Beauharnois-Salaberry bylaw that designates areas where wind turbines may be installed within its territory.

Bylaw No. 334, which was approved at the provincial level on Nov. 7, sets out various restrictions and protections for wind energy development, particularly in terms of agricultural land and noise levels.

The bylaw was adopted by the MRC during the regular council meeting on Sept. 16. It excludes 93 per cent of the territory from the installation of any type of wind turbine. Compatible zones therefore account for just seven per cent of the territory, and air corridors under NAV Canada’s jurisdiction must be subtracted from this area.

Essentially, Saint-Urbain-Premier is the only municipality where wind turbines can be installed within the parameters established by the bylaw. “But even then, the municipality must genuinely want a project. There is no mechanism that forces municipalities to host them. Anyone who claims otherwise, is flat-out lying,” said MRC prefect Miguel Lemieux, who is also the mayor of Salaberry-de-Valleyfield.

Lemieux acknowledged that a company is currently working on a project that would be entirely located in Saint-Urbain-Premier. “It is the only municipality in the MRC de Beauharnois-Salaberry that is in discussions with a company,” he confirmed. “We know that a project proposal will not be submitted as part of the upcoming call for tenders,” he added.

The first round of tenders is set to close in February 2027, and according to Lemieux, the company has indicated their proposal will not be ready by this deadline.

“There is only one project in Saint-Urbain-Premier. Social acceptance is very high in that area,” said Lemieux, while noting the bylaw’s rapid adoption was specifically intended to allow the municipality to move forward with the project.

“The other MRCs in Quebec will have to follow our lead. The MRCs have until 2028 to adopt a bylaw that provides a framework to their municipalities. We did it early in the process because Saint-Urban-Premier had a potential project. There are no projects on the table in the other municipalities,” said Lemieux.

The MRC de Beauharnois-Salaberry has been careful not to take position either for or against wind energy development. “What we have always said is: submit a project, and we will evaluate it on its own merits. We don’t have a position for or against it. If the project looks promising, we are for it. If it does not make sense, we will be against it,” said Lemieux.

Wind energy projects that are presented to Hydro Québec must not only comply with the MRC’s bylaw, they must also be approved by municipal resolution. “A municipality cannot be forced to host a project. The municipality really has to want it,” said Lemieux.

Latest stories

Police boost Ormstown patrols after fourth suspicious fire

Sarah Rennie - LJI Reporter

Caisse Desjardins in Saint-Chrysostome to close

Sarah Rennie - LJI Reporter

Fire forces Brasserie Barabas to close

The Gleaner

Leave a comment

* By using this form you agree with the storage and handling of your data by this website.